Problem Statement
As ERDC expands its AI/ML and High-Performance Computing capabilities, there is
a growing demand for infrastructure that can support accelerated deployment
timelines and the power and cooling demands of next-generation accelerators. A
modular, rapidly assembled data center for future capacity requirements is
needed.
Project Objective
This Individual Program Requirement seeks to identify “baseline” systems for integrated Modular Data Centers (MDCs) capable of sustaining a minimum of 1 MW Information Technology (IT) critical load. The MDC should be capable of supporting high density and power requirements of CPU and GPU architectures, including up to ~300 KW per rack and ~450 lb per sq ft. The MDC should include all necessary Uninterruptible Power Supply (UPS) systems, backup power generation, precision cooling, and fire suppression systems integrated into a containerized solution. ITL will gain a comprehensive understanding of industry capabilities to provide resilient and secure (ICD-705) operations for HPC and AI systems. The final deliverable should be manufactured off-site, transported, and rapidly assembled within a 6-month timeframe to support next-generation workloads with rigorous liquid cooling demands. Furthermore, this initial deployment must serve as a scalable baseline architecture that can be rapidly duplicated and expanded to meet future capacity requirements.
Requirements
Submissions should consider the design, integration, and deployment of a highly flexible MDC architecture that provides a fully integrated and secure compute environment and address the following key areas:
Constraints and Considerations:
Note: Submissions should NOT include confidential or proprietary details. Submissions may be shared with other ERDC teams if there is an apparent fit with other ERDC projects.
Estimated Government Funding Profile
The government would like to see a variety of scalable technical solutions not bound by a minimum or maximum funding level. While funding is available for this effort, a minimum and/or maximum amount will not be provided at this time.
This project does not commit the government or ERDCWERX to pay any costs incurred in preparation of a response or guarantee a contract.
Estimated Period of Performance
Solutions should propose a timeline detailing the delivery and deployment of the fully integrated and deployed secure MDC.
Desired End State
ERDC gains an understanding of the available industry solutions related to rapidly deployable, scalable, and highly secure self-contained Modular Data Center (MDC) infrastructure.
Evaluation Criteria
Submissions will be evaluated based on the criteria described in the CSO Solicitation document. Additional criteria specific to this project are listed below:
All resultant contracts will be firm-fixed price. All items, technologies, and services (including research and development) procured via this CSO are treated as commercial. Applicants from universities and/or non-profit organizations should be aware that commercial clauses will be integrated into the award and should coordinate proposals with associated legal counsel prior to submission.
Proposed project milestones include:
|
August 31, 2026 |
Project Announced, Submissions Open |
|
September 9, 2026 |
Question Period Ends |
|
October 30, 2026 |
Submissions Close |
|
October 30, 2026 |
ERDC Conducts Reviews |
|
November 2026 |
Downselected Vendors Notified |
How to Participate
Qualified parties may submit by completing a submission form and uploading required documentation as defined in the CSO Solicitation document.
1. Review CSO
Solicitation document
2. Review FAQs
3. Complete the submission
form
Submission Instructions:
This solicitation is issued consistent with the authority granted to the U.S.
Army Engineer Research and Development
Center (ERDC) through the establishment of its
Commercial Solutions Opening (CSO), W912HZ26SC006. Submissions must follow
the requirements as detailed in the CSO Solicitation document.
Questions:
Interested parties may submit questions using this form until
September 9, 2026.
Submissions must meet stated requirements and be received no later than 4:00 pm CT on Wednesday, October 30, 2026.